Hi,
we want to perform project budgeting and tracking at acitivity level, but I couldn't find any inquiry or report where I can do this.
If I call project budget balances there is one budget line for each activity but the activity isn't shown and I can't personalize the fied to this form.
Does anyone know if there is such a query/report and if so where?
Thx
Rene
===========================================================================================================
1. Create project budget cost line on activity level
![]()
2. Post project purchase order receipt and item requirement delivery with reference to activities => Posted project transactions
![]()
3. Registered item requirements with reference to acitivity ==> Commited cost
4. Project budget balance show 3 different budget lines, but it doesn't show the acitivity number and I'm not able to personalize the form.
![]()