We have an issue when a PO is matched to an invoice with a variance e.g.
PO 1 item £1000
Invoice 1 item £990
We match to the PO and manually update the unit price to reflect the £10 difference. We then end up with the following when the invoice is posted
£990 in our WIP GL account
£1000 on our project item WIP
So the project takes the value from the PO and the GL from the invoice meaning that our WIP reconciliation is out by £10.
Just trying to establish if this is a bug or a config issue?